Foothill Gold Line Light Rail Project from Glendora to Pomona Reaches 50% Construction Completion – QNT Press Release


Elected officials from the federal, state, county and local levels celebrate historic milestone achievement

SAN DIMAS, Calif., June 17, 2022 /PRNewswire/ — Today, the Foothill Gold Line Construction Authority (Construction Authority) held a press conference to celebrate the 9.1-mile, four-station Foothill Gold Line light rail project from Glendora to Pomona reaching 50% construction completion. The celebration took place at Rhoads Park in San Dimas, Calif.just steps away from the project corridor and one of four new light rail bridges being constructed to carry future light rail trains and passengers over major streets. Construction on the project began in July 2020 and, despite building in the midst of the COVID-19 pandemic, continues to remain on schedule to be completed in early 2025, when it will be turned over to LA Metro for training and pre-revenue service (Metro determines when passenger service starts) .

“It is a great achievement for our team, our contractor and the entire County of Los Angeles to have been able to keep this important regional infrastructure project on schedule during the first years of the Pandemic,” stated Foothill Gold Line Board Chairman and Claremont Mayor Pro Tem Ed Reece. “We are now just a few short years away from delivering light rail to more of the San Gabriel Valley and one step closer to completing our agency mission of connecting Los Angelesthe San Gabriel Valley and Inland Empire by light rail.”

To reach the halfway milestone, the design-build team of Kiewit-Parsons, a Joint Venture (KPJV), with over 350 staff and crew members, have to date expended nearly 1.1 million work hours designing and constructing the various elements that make up the light rail project. Here is a highlight of the work completed or underway so far:

  • Project Design: 100% Complete
  • Relocation of Freight Track Within Shared Corridor to Make Room for New Light Rail Tracks: 98% Complete
  • Reconstruction of 21 At-Grade Crossings: 91% Complete
  • Construction of 19 New or Renovated Bridges: 39% Complete Overall
    • Freight…